BOQ quantity versus procurement quantity
The BOQ quantity describes the measured work or installed requirement. Procurement quantity may be higher where cutting, routing, packaging or installation conditions create expected losses. Keep the two values visible so a reviewer can understand the difference.
A simple planning formula is: procurement quantity = base quantity × (1 + wastage percentage ÷ 100). For example, a measured 100 m cable run with a hypothetical 5% allowance gives 105 m for planning. This example is not a recommendation for every cable run; measure routes and apply project-appropriate allowances.
Items to check before ordering
- Cable type, conductor size, insulation, installation method and actual route length.
- Conduit, trunking, bends, couplers, boxes, supports and termination accessories.
- Lighting fittings, switching, sockets and compatibility with specified accessories.
- Distribution boards, protective devices, breaking capacity and coordination requirements.
- Earthing and bonding conductors, electrodes, clamps and testing requirements.
- Packaging quantities, minimum order quantities, delivery lead times and approved brands.
Reduce avoidable procurement errors
Normalize units before combining quantities. A cable length in metres should not be mixed with drum counts without a conversion. Keep pack sizes and purchase multiples in separate fields. Verify stock, delivery lead time and quotation validity with suppliers rather than treating an illustrative catalogue as live inventory.
Use the MTO with the BOQ
Begin with the reviewed electrical BOQ, calculate procurement allowances, compare the result against supplier quotations and then update the project cost estimate. The PRIWAD demo supports CSV export; transferring data to the separate Excel workbook is a manual workflow, not a live synchronization.